Project Background
Installation of a 250,000 gallon per day wastewater treatment plant, 24-inch to 42-inch gravity collection system, lift station, associated site improvements, office, lab and site security to meet TCEQ regulations. The project is scheduled to be ready to receive flow in April of 2021.
CID 01: Construction Complete
CID 02: In construction, 37% complete
CID 03: In construction, 30% complete
CID 04: In design, 95% complete
CID 05: In design, 60% complete
Project Summary
All easements have been acquired for CID 01 through 04. Easement acquisition for CID 05 is currently underway. Bidding is scheduled for early summer 2021 for CID 05.
Construction Cost Estimate: $19,598,500
Awarded Contract: CID 01 Bolton Road $1,096,112.97
CID 02 WWTP Site Work and Collection System $10,555,909.56
CID 03 Wastewater Treatment Plant $1,887,500
CID 04 Office and Lab at WWTP – In design, estimated at $1,053,398.50
CID 05 Phase IB Collection System – In design, estimated at $4,234,000.00